Project Details

July 10, 2026
El Paso Highway Bridge

Project Number: GEO-2025-007

Client: TxDOT

Status: Planned

Priority: High

Start Date: Jan 14, 2026

End Date: Feb 03, 2026

Total Duration: 18 days

Budget: $275,000.00


Location

I-10 & Airway Blvd, El Paso, TX 79925

Coordinates: 31.7619000, -106.4850000


Description

Foundation investigation for bridge replacement. Rock coring, load testing.

Duration Breakdown

Mobilization: 2 days

Investigation: 15 days

Demobilization: 1 days


Total: 18 days

This project is overdue!