CIVILNEX

July 10, 2026

ABC

123 Apr 09, 2026
Total Cost

$281,675.00

Draft
Back to List
Description Quantity Unit Unit Price Total Actions
Mobilization
$45,000.00
Mobilize/Demobilize Equipment
1.00 LS $45,000.00 $45,000.00
Helical Piles
$72,125.00
SS5 (1.5" Square Shaft)
$26,350.00
SS5 Lead Section - 8/10 (8" & 10" helices)
15.00 EA $650.00 $9,750.00
SS5 Lead Section 10/12 (10" & 12" helices)
10.00 EA $850.00 $8,500.00
SS5 Extension Shaft - 5 ft
40.00 EA $120.00 $4,800.00
SS5 Extension Shaft - 7 ft
20.00 EA $165.00 $3,300.00
SS150 (1.5" Square Shaft)
$23,975.00
SS150 Lead Section - 10/12 (10" & 12" helices)
12.00 EA $950.00 $11,400.00
SS150 Lead Section - 12/14 (12" & 14" helices)
8.00 EA $1,150.00 $9,200.00
SS150 Extension Shaft - 5 ft
25.00 EA $135.00 $3,375.00
SS175 (1.75" Square Shaft)
$21,800.00
SS175 Lead Section - 10/12 (10" & 12" helices)
10.00 EA $1,100.00 $11,000.00
SS175 Lead Section - 12/14 (12" & 14" helices)
6.00 EA $1,300.00 $7,800.00
SS175 Extension Shaft - 5 ft
20.00 EA $150.00 $3,000.00
Brackets & Connections
$6,925.00
New Construction Brackets (C150-0121)
30.00 EA $85.00 $2,550.00
Heavy Duty Brackets (C150-0298)
15.00 EA $125.00 $1,875.00
Structural Bolts & Hardware
1.00 LS $2,500.00 $2,500.00
Testing & Inspection
$10,500.00
Proof Load Testing
5.00 EA $1,200.00 $6,000.00
Third-Party Inspection
3.00 Days $1,500.00 $4,500.00
Overhead & Profit
$45,000.00
Overhead & Profit (15%)
Calculated as percentage of direct costs
1.00 LS $45,000.00 $45,000.00
Contingency
$30,000.00
Contingency (10%)
For unforeseen conditions
1.00 LS $30,000.00 $30,000.00
Grand Total: $281,675.00